Bay Area Residential Design & Construction Timelines

Examples Based on Recent Projects In San Francisco, CA

Read more about our process and costs.

 

Project timelines

  • Typically our construction schedule is booked about six months out. You should plan for a minimum of four months for design development and permitting, pending project size. Simple projects such as kitchen or bathroom remodels move fairly quickly because there is less design work and permits can be done over the counter. If you are remodeling more of your home including changing walls, adding square footage, etc., then you can assume design and permitting could take a year or more, pending which reviews are required by the city for your specific project.

Examples

  • 200 sf full kitchen remodel with partial wall removal, all interior work.

    Design and Permitting: 4 months | Construction: 4-6 months

  • 500 sf basement master suite remodel, minor exterior changes, no digging/excavation.

    Design and Permitting: 6-8 months | Construction: 7-9 months

  • 750 sf attic remodel / vertical addition / new floor, exterior changes.

    Design and Permitting: 10-14 months | Construction: 11-14 months

  • 2000 sf whole home remodel, minor exterior changes.

    Design and Permitting: 8-10 months | Construction: 11-14 months

 

NOTES

When you’re planning your project, keep in mind that your project budget & schedule will be impacted by permits & historical regulations.

Some more information on the Permit Process can be found here.